Client: Matricon
Project Value: Approx $30M
Location: Curtin Airforce Base, Curtin
CID Consultants were appointed by lead service contractor Matricon to complete the hydraulic design for the 600 man expansion of the Curtin Detention Centre.
Matricon were commissioned by direct contractor Complete Site Services who had been awarded contract to supply donga style accommodation and recreation and service facilities for the expansion. CID completed all hydraulic infrastructure design along with the design of the wet and dry mess.
The scope of works (completed) included the provision of;
-
hot and cold water service infrastructure
-
sanitary drainage
-
gas supply
-
fire main
-
Wet and Dry mess water/sanitary/gas layout design
This project was constructed as an accelerated program. It required efficient ongoing communication and liaison with site personnel as the design continued while construction was in progress.